Internal robotic weld build-up of Pressure Vessel flange

Using robot welding can reduce shut-down time drastically

Internal robotic weld build-up of Pressure Vessel flange
1.2
Ton of filler metal
22.5
Km weld
4.5
Days spent welding
70
Percent time reduction

Due to internal corrosion of the a deaerator on an on-shore plant, Effee was contracted to butt-weld in a special flange on the horizontal part of pressure vessels, this to build up material thickness to a minimum as original thickness. This was carried out using a welding robot that hung from a specially made bracing that was mounted on the flange. Only one welding procedure was used, which was specifically for this purpose. The welding procedure also included post-weld heat treatment (PWHT), carried out with by subcontractor. The flange surface was finally machined due to corrosion of the flange surface, as well as large dimensional deviations from its original design.

Get in touch

We would love to talk business with you. Give us a call at +47 466 83 577 or email us at [email protected]

You can also talk directly to Eirik, for indepth knowledge about this project.

Eirik Belland
Eirik Belland
Managing Director, Co-Founder

Services used in this project

Robot welding

Robot welding in-field - repair, not replace.